<img alt="" src="https://secure.norm0care.com/146994.png" style="display:none;">

Every layer matters. A holistic approach to quality control can be useful.

[fa icon="calendar'] Dec 7, 2017 10:00:00 AM / by Mark McGivern, CSI, Aff. M. ASCE

Whose fault was it? This is a frequently asked question when an exterior wall leaks, rots, or falls down. During a construction failure investigation, contractors often highlight the defects of other trades that affected their work. Defects include those that were documented during construction but not corrected. This may be due to timing and scheduling constraints.

Often the findings from building failures are then used going forward as best practices for new construction. However, those learned best practices should not be the only guideline. Critical areas that need to be addressed include the points of intersection, as many times there are multiple layers of building materials which are put in place by various subcontractors. This step is known as a pre-covering inspection. A pre-covering inspection of each layer at each wall area would be ideal, so problems at each layer do not accumulate, influence other layers, or get concealed.

The following article looks at examples of pre-covering inspection criteria to illustrate the influence each layer may have. Continue reading….

 

Read More [fa icon="long-arrow-right"]

Man with Walnut Allergy Dies on Construction Site

[fa icon="calendar'] Nov 30, 2017 10:00:00 AM / by Clark Griffith, AIA

Alberta Occupational Health and Safety investigators are looking into the death of an Edmonton man with a nut allergy who died after visiting a work site where walnut shells were used to blast paint off walls.

Recently alternatives to sandblasting including the use of walnut shells, coconut shells and corn cobs have been widely used in the construction industry over the last decade.

Continue to full article...

Read More [fa icon="long-arrow-right"]

Stricter Building Codes Saved Florida’s Commercial Buildings from Irma’s Wrath

[fa icon="calendar'] Nov 28, 2017 10:00:00 AM / by Mark McGivern, CSI, Aff. M. ASCE

Hurricane Irma bore down hard on single-family homes, severely damaging many. At the end of September residential insurance claims had been cited around a half-million. The story, however is quite different for commercial and industrial buildings where insurance claims had been cited around 25,000.

This is mainly due to the stricter building codes that were put in place following the wrath of Hurricane Andrew in 1992. “Designed to withstand a Category 5 hurricane with winds of 175 mph, the Florida building code is the accepted benchmark for hurricane protection nationally.”

“Florida significantly strengthened its defenses after hits from past major hurricanes, and those improvements were instrumental in helping the state weather this potentially devastating storm,” Levy notes. “As a result, damage to Florida commercial real estate is relatively minor outside of the Keys.”

Continue to full article….

Read More [fa icon="long-arrow-right"]

Water Damage During Construction

[fa icon="calendar'] Oct 11, 2017 3:55:00 PM / by Robert Pfeifer, AIA

 

Read More [fa icon="long-arrow-right"]

If All Else Fails – Communicate Effectively!

[fa icon="calendar'] Aug 16, 2017 12:37:00 PM / by John R. Manning, PE, CCM, LEED

 

Many projects often bring to mind the famous line from Cool Hand Luke – “What we've got here is a failure to communicate.”

 

One of the definitions of communication from Merriam Webster Dictionary is “a technique for expressing ideas effectively.” On today’s projects, everyone on the project seems to be communicating, whether that be talking, emailing and/or sending correspondence, but the reality is that no effective communication is occurring. Many times, project participants are overwhelmed with the amount of correspondence and get extremely defensive of their positions, especially if they miss something. We may not have a failure to communicate but it appears many times that we have a failure to communicate EFFECTIVELY.

So how do we address this failure to communicate effectively??? I still remember one of my first classes on public speaking where the professor laid out a simple yet effective outline for a speech. He said in the Opening you tell them what you plan on speaking about; then in the Body you tell them what you are speaking about; and, finally, in the Conclusion you tell them what you told them! This has been shown to be an extremely effective means of communicating in speech to inform someone of a topic.

Read More [fa icon="long-arrow-right"]

The Importance of a Quality Management Plan and Why it Should be Completed Early!

[fa icon="calendar'] Aug 8, 2017 10:30:00 AM / by John R. Manning, PE, CCM, LEED

 

Quality on a project, many times, is one of the last considerations for an Owner whom usually focuses first on cost and then schedule.

 At the end of the day, the Quality of a built project is extremely critical for a lot longer than the time it took to design and build it. In the Project Management Plan, there should be a Quality Management Plan portion. In that segment the Project Manager should outline who will be responsible for delivering quality on a project. This starts first with a good design. One of the first steps the Owner’s Representative can do is to develop a Differentiation Document that clearly outlines who will be responsible for what in a Project, similar to the following example of a site and pool area development.

Read More [fa icon="long-arrow-right"]

Why early clarification of the Owner’s Objectives is CRITICAL

[fa icon="calendar'] Jul 24, 2017 1:32:00 PM / by John R. Manning, PE, CCM, LEED

 

As an Owner’s Representative one of the MOST CRITICAL tasks you must do is to ensure that the Owner’s Objectives are clear. Having testified in court on construction management issues, I have learned one of the most difficult things to overcome is an Owner who believes they bought “X” and received “Y” due to the documents not being clear. 

 

When the Owner’s Objectives do not have adequate detail to allow the Contractor to build the project as the Owner desired, conflicts are sure to follow. Furthermore, some of the most difficult obstacles to overcome on a project are Owner directed changes that impact the schedule after a contract is let. Contractors tend to price Impact Charges on these changes which causes the price of the desired changes to increase to an amount that far exceeds the cost if it had been included in the original contract.

Read More [fa icon="long-arrow-right"]

How should an Owner select a Design Consultant and Contract for Design on a Project?

[fa icon="calendar'] Jul 11, 2017 12:55:00 PM / by John R. Manning, PE, CCM, LEED

The most effective use of an Owner’s Budget on a project is to ensure that they have a good design. The lack of a complete and coordinated design on a project has resulted in many failed projects.

 

Going cheap on a design team is the worst area to try to cut money on a project. This does not mean overpaying for design but it does mean getting the right design team for the project and paying a fair value for the design services as well as holding their feet to the fire to achieve a complete design. As an Owner’s Representative, it is key for us to help the Owner in these tasks.

The best process to select a design professional is a two-step process. The first step will be a submission of qualifications (RFQ) and the second step is a submission of pricing (RFP). The reason we recommend a two-step process is to ensure that first we narrow the field down to design firms who are qualified for the type of project they are designing and secondly, separately, get pricing from that narrowed down field.


RFQ Process

A detailed Request for Qualifications process is the first step. The Owner’s Representative, with input from the Owner, should develop a list of Design Consultants to solicit qualifications from on a project. The Request for Qualifications Package should provide the Project Definition/Scope/Client Requirements in narrative form and the required Time of Performance from the Milestone Schedule for the Design Milestones which will help the Design Consultant understand what the project will entail. The Request for Qualifications should request the following responses from the design firms:

1. Firm’s Approach to the Project

As the Owner’s Representative, you want to understand how the Design Team will approach this Project. How may design evolution packages do they believe are necessary? Do they have a unique approach to the Project that would make them the better choice for this Project?

2. Firm’s Experience in Similar Projects (usually at least five similar projects)

You will want to know what other projects, like the one you are managing for the Owner, they have done in the past. This will help you understand their capabilities on completed projects and allow you to gauge their capabilities.

Read More [fa icon="long-arrow-right"]

Why have a Master Schedule? What should be included in that schedule?

[fa icon="calendar'] Jun 26, 2017 10:53:00 AM / by John R. Manning, PE, CCM, LEED

 

In parallel with the development of the budget is the development of the Master Project Schedule. This schedule will outline the goals of the Owner for the project with respect to time.

The Owner’s representative should develop various alternative approaches for phasing, sequencing, management and implementation of the project from due diligence through commissioning. This schedule is an outline of the key activities necessary to complete the project. Then based upon review with the Owner, the Owners’ Representative will prepare a final Master Schedule that will detail the overall time related goals for the project. This schedule should be presented in a format that the Owner can comprehend even if it is developed in a sophisticated scheduling program like Primavera P6. It is critical that the Owner’s Representative get acceptance of the time line from the Owner prior to finalizing the Master Schedule.

Read More [fa icon="long-arrow-right"]

Preliminary Cost Investigations and the Importance of a Detailed Budget

[fa icon="calendar'] Jun 21, 2017 9:55:27 AM / by John R. Manning, PE, CCM, LEED

 This is the sixth post in our year-long series about the best ways to work with your Owner's Representative.  You can view all of the series posts here.

The most critical segment of the pre-design phase of your project is the development of a sound budget through good preliminary cost investigations.

 

A project can be made or lost in those crucial first few days or weeks if careful thought is not put into the budget. Once the budget is set and the Owner gets its funding it becomes an uphill battle to get more funding so all budgets need to be reviewed by everyone who has a stake in the project from the Owner’s side. The budget should be broken out in adequate detail to allow everyone to understand what is included in the budget and what is not included in the budget.

Most of the time budgets are developed with little, if any, design documentation. This initial budget estimate may be required prior to any plans or sketches and be based solely on a “concept” or “program,” hence the need for a well thought out and written Scope or Project Requirements, which should be developed in parallel with the budget and will provide the detail of what is included in the budget.

Actual estimating will typically be limited at this stage to broad budget type numbers based upon areas. Those areas should be included in a written Scope or Project Requirements (Program). In any budget breakdown, notes should be added to line items to ensure that others understand what was considered and be able to follow the budget logic.

Read More [fa icon="long-arrow-right"]